No. Northumberland/26/03819/FUL
Undecided
Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland
Proposal
Development of electricity grid connection between Blyth Substation and consented Cambois Data Centre Campus Substation 1 (NCC Ref. 25/03390/REM), comprising installation of underground 132kV electrical connection and communication cables, and temporary construction activity including excavation and backfilling of ground trenches, horizontal directional drilling, erection of construction fencing and associated works
Key dates
- Started2 November 2026
Get the app