No. Fife/19/02750/NMV1
Granted with conditions
Ferrymuir Energy Battery Storage Stratheden Cupar Fife KY15 5RW
Proposal
Non-Material Variation for extension of existing concrete battery bases, the repositioning and consolidation of existing battery racks, and the installation of 12 additional DC battery containers on the vacated battery-unit bases, retaining the existing maximum import and export capacity of 49.9 MW to planning permission 19/02750/FULL
Key dates
- Started10 August 2026
- Decided27 October 2026